INSTALLATION FOR PREFINISHED PARQUETS

Make sure that the floor is sufficiently dry before fitting. Check the humidity level in new contructions. During / after laying, humidity level should ideally be between 45-60% and room temperature between 18 °C and 24 °C.

To start the installation procedure, first lay down the foam sheet and place the first row so that the grooves face the wall. You should use wedges between the first row and the wall to provide room for potential expansions.
The pieces should be glued on the grooves and should be tightly joined to the tongue of the piece in the previous row by applying a moderate force with a wooden block.
The excess glue should be wiped off by a clean cloth. The next row should start with the remaining last piece of the previous row and the connection lines of the successive rows should be shifted by at least 50 cm.
After the pieces are tightened by a suitable tool, the wedges should be removed and the gap between the wall and the flooring should be covered by skirting board.

Note:
Please open the packaging only just before installing the prefinished parquets. It is recommended to lay the boards in the direction of incoming light. Responsibility belong to buyer if installation is not handled by Serifoglu licensed dealers.